MBA
624Name: Yonatan Balin

Skill
Builder  #2
1. 
General Foundry, Inc., a metal works plant in
Milwaukee, has long been trying to avoid the expense of installing air
pollution control equipment. The local environment protection group has
recently given the foundry 16 weeks to install a complex air filter system on
its main smokestack. General Foundry has been warned that it may be forced to
close unless the device installed in the allotted period. Lester Harky, the
managing partner, wants to make sure that installation of the filtering system
progressed smoothly and on time.
General Foundry has identified the following eight
activities that need to be performed and their sequential relationship.

Activity

Description

Time
(weeks)

Immediate
Predecessors

A

Build internal components

2

B

Modify roof and floor

4

C

Construct collection stack

2

A

D

Pour concrete and install frame

4

A, B

E

Build high-temperature burner

4

C

F

Install pollution control system

3

C

G

Install air pollution device

5

D, E

H

Inspect and test

2

F, G

Construct
the appropriate network diagram. (10 points)
Which jobs can be delayed without delaying the project
completion time? (10 points)
Can
General Foundry complete the project on time? Why or why not? (20 points)
Suppose
Lester wants to shorten the completion time and his options are:
(1)Reduce activity D by one week, which costs $700/week;
(2)Reduce activity E by one week, which costs $800/week;
(3)Reduce activity G by one week, which costs $1000/week;
If General Foundry will save $2000 for each week that the
earliest completion time is reduced, which single option, if any, should Lester
choose? (10 points)
2. 
The following table
represents a plan for a project:

Time Estimates (days)

Job No.

Predecessor Job(s)

Optimistic

Most likely

Pessimistic

A

1

2

3

B

2

3

4

C

A

4

5

6

D

B

8

9

10

E

C, D

2

5

8

F

D

4

5

6

G

E

1

2

3

Construct
the appropriate network diagram. (10 points)
What
is the critical path? (10 points)
What
is the expected completion time for the project and what is the variance
of project completion time? (20 points)
Is
the probability that the project will take less than 18 days to complete
larger than 50% or smaller than 50%? (10 points)
skill_builder_2_s16.docMBA 624
Name: Yonatan Balin
Skill Builder #2
1. General Foundry, Inc., a metal works plant in Milwaukee, has long been
trying to avoid the expense of installing air pollution control equipment. The
local environment protection group has recently given the foundry 16 weeks
to install a complex air filter system on its main smokestack. General
Foundry has been warned that it may be forced to close unless the device
installed in the allotted period. Lester Harky, the managing partner, wants to
make sure that installation of the filtering system progressed smoothly and
on time.
General Foundry has identified the following eight activities that need to be
performed and their sequential relationship.
Activity
Description
A
B
C
D
E
F
G
H
Build internal components
Modify roof and floor
Construct collection stack
Pour concrete and install frame
Build high-temperature burner
Install pollution control system
Install air pollution device
Inspect and test
Time
(weeks)
2
4
2
4
4
3
5
2
Immediate
Predecessors
–A
A, B
C
C
D, E
F, G
a. Construct the appropriate network diagram. (10 points)
b. Which jobs can be delayed without delaying the project completion time? (10
points)
c. Can General Foundry complete the project on time? Why or why not? (20
points)
d. Suppose Lester wants to shorten the completion time and his options are:
(1) Reduce activity D by one week, which costs $700/week;
(2) Reduce activity E by one week, which costs $800/week;
(3) Reduce activity G by one week, which costs $1000/week;
If General Foundry will save $2000 for each week that the earliest
completion time is reduced, which single option, if any, should Lester choose?
(10 points)
2. The following table represents a plan for a project:
Time Estimates (days)
Job No. Predecessor
Optimistic
Most likely
Job(s)
A
1
2
B
2
3
C
A
4
5
D
B
8
9
E
C, D
2
5
F
D
4
5
G
E
1
2
Pessimistic
3
4
6
10
8
6
3
a. Construct the appropriate network diagram. (10 points)
b. What is the critical path? (10 points)
c. What is the expected completion time for the project and what is the
variance of project completion time? (20 points)
e. Is the probability that the project will take less than 18 days to complete
larger than 50% or smaller than 50%? (10 points)

Purchase answer to see full
attachment




Why Choose Us

  • 100% non-plagiarized Papers
  • 24/7 /365 Service Available
  • Affordable Prices
  • Any Paper, Urgency, and Subject
  • Will complete your papers in 6 hours
  • On-time Delivery
  • Money-back and Privacy guarantees
  • Unlimited Amendments upon request
  • Satisfaction guarantee

How it Works

  • Click on the “Place Order” tab at the top menu or “Order Now” icon at the bottom and a new page will appear with an order form to be filled.
  • Fill in your paper’s requirements in the "PAPER DETAILS" section.
  • Fill in your paper’s academic level, deadline, and the required number of pages from the drop-down menus.
  • Click “CREATE ACCOUNT & SIGN IN” to enter your registration details and get an account with us for record-keeping and then, click on “PROCEED TO CHECKOUT” at the bottom of the page.
  • From there, the payment sections will show, follow the guided payment process and your order will be available for our writing team to work on it.